By providing your contact information to Desert Land Group, your personal information will be processed in accordance with Desert Land Group's Privacy Policy. By checking the box(es) below, you expressly consent to receive marketing or promotional real estate communication from Desert Land Group in the manner selected by you. For SMS text messages, message frequency varies. Message and data rates may apply. Consent is not a condition of purchase of any goods or services. You may opt out of receiving further communications from Desert Land Group at any time. To opt out of receiving SMS text messages, reply STOP to unsubscribe. SMS text messaging is subject to our Terms of Use.

Thank you for your message. We will be in touch with you shortly.

Explore Properties
Background Image

Zoning Request for Storage Units on Northern Edge of Havasu OK’d

Plans to amend the zoning of several lots along State Route 95 at Lake Havasu City’s northernmost edge ultimately received a recommendation of approval from the Planning and Zoning Commission. But before voting, the commission added a couple extra stipulations to ensure a visual buffer is put in place in conjunction with a planned storage unit development further back from the highway.

The rezone request for a total of six lots north of The Shops at Lake Havasu along the lakeside of the highway to the intersection with London Bridge Road originally came to City Council in April, but was denied due to councilmembers’ concerns that the changes would allow storage units along the highway on two of those lots. Councilmembers noted that area is the first thing that people see when they drive to Lake Havasu City from the north. Desert Land Group is handling the rezone requests from two separate owners of the two lots. CEO Mychal Gorden told the commission that Desert Land Group worked with the owners to address the council’s concerns and came up with a new rezone request that would create a one acre commercial buffer between the highway and plans for 4.21 acres of storage units.

The new development plan proposal includes all of a lot owned by Lakeside Development along with parts of the neighboring lot to the south, owned by Jason and Christine Anderson. Lake Havasu City Planner Luke Morris said the rest of the vacant lot owned by the Andersons will retain its current zoning, which is set up to accommodate a car dealership.

After extensive discussion, the commission decided to include two extra conditions that would further limit storage units’ visibility from the road. The first requirement added to the requested planned development requires planned landscaping on the newly-created commercial buffer lot be completed at the same time that the storage units are developed. The commission also added a requirement that all of the storage units closest to the highway have “architectural character” on the side facing SR95 to avoid blank metal walls from being visible from the road.

The commission voted 7-0 to approve the requested rezone with the added conditions.

During the meeting, Luke Morris told the commission that city staff recommended adding a condition that the proposed buffer lot along the highway be developed prior to, or at the same time as, the plans for the storage units on the larger lot. That particular recommendation wasn’t included in the original staff report but Morris said staff decided to include it after further review.

“We thought it might be good to ensure the buffering is done before the proposed storage units,” Morris said.

Chairman Jim Harris said he felt that particular requirement placed an undue burden on the developer. Gorden said that recommendation caught him by surprise. He said he opposed the city’s recommendation because it had not previously been included in any of the reports or notices sent out by the city.

But Commissioner Suzannah Ballard questioned the value of including a one-acre buffer along the highway without any assurances that development will ever actually materialize. She pointed out that if that property remains undeveloped, the planned storage units would still be the first thing people see when they drive into Havasu.

Gorden suggested requiring the landscaping be completed on the proposed new buffer lot along the highway, rather than requiring everything on the lot be developed first, as a compromise.

Commissioner Chad Nelson suggested placing additional architectural requirements on the highway-facing walls of future storage units closest to SR95 as an additional way to minimize the potential visual impact of the storage near the north entrance of town. Gorden said he was okay with that condition, adding that the current plans are for all of the storage units to have an upscale and visually pleasing appearance.

When the properties were discussed by the council in April, the request included a rezone for four additional smaller lots on the corner of the property along the highway that councilmembers indicated they supported. On Wednesday, those four lots were split off into a separate rezone request that was largely the same as the plans presented in April. Those plans allow any general commercial use on the property except for storage units. Once developed, those commercial properties will serve as a buffer between SR95 and the existing storage units that have already been built on three adjacent lots farther from the highway.

The commission unanimously approved the rezone request for the four smaller lots as written, with a planned development that bars storage units, mandates the façade facing the highway include “architectural character,” and keeps the maximum building height at 36 feet, rather than the typical 25-foot limit for general commercial zoning.

All six lots seeking a rezone are part of a 37-acre planned development approved by City Council in 2007 called Havasu Auto Mall that envisioned car dealerships and some smaller businesses, restaurants, or retail-type businesses immediately north of the shops. Although three businesses moved into the lots farthest to the south, the rest of the development has not proceeded as planned. Gorden said these rezone requests are meant to free the lots from the development plans approved 14 years ago and allow for more flexibility for businesses to develop the lot to suit their needs.

The Planning and Zoning Commission’s recommendation will be forwarded to the City Council, which will hold another public hearing for both rezoning requests at a future meeting before taking a final vote to approve or deny the requests.